Patti's School Progrss - January 2009
We are very close to having enough funds to complete the first floor of Patti's School. Please consider how you can help the children be in the building by September 2009.
funds required to complete Patti's School first floor for occupancy
Haitian to US exchange rate: 7.70
| Haitian | US $ | |||
|---|---|---|---|---|
| Materials for floor and 20 columns | ||||
| 4 loads "LaBoule" sand | 4,000 | 519.48 | ||
| 2 loads broken river rock | 2,000 | 259.74 | ||
| 4 loads backfill | 3,000 | 389.61 | ||
| Steel for 1st floor and walls | ||||
| 1 ton 1/2" rebar | 15,000 | 1,948.05 | ||
| 1/2 ton 1/4" rebar | 5,000 | 649.35 | ||
| 20 pc 5/8" rebar | 4,000 | 519.48 | ||
| 1 roll tie wire | 600 | 77.92 | ||
| Transportation for steel | 500 | 64.94 | ||
| 260 bags cement for floor and columns | 13,000 | 1,688.31 | ||
| Form lumber rental | 4,470 | 580.52 | ||
| 3,500 concrete blocks | 2,200 | 285.71 | ||
| Cement to install blocks | 1,000 | 129.87 | ||
| Mason and helpers | 3,700 | 480.52 | ||
| General labor for floor and walls | 28,900 | 3,753.25 | ||
| Plumbing materials | 3,350 | 435.06 | ||
| 4 metal doors, locks and 2 coats primer | 16,000 | 2,077.92 | ||
| 4 office windows and security bars | 9,500 | 1,233.77 | ||
| Electrical | 13,800 | 1,792.21 | ||
| Sub total for floor columns and walls | 16,885.71 | |||
| Total slab | ||||
| Labor for top slab | 27,200 | 3,532.47 | ||
| 1 ton 1/2" rebar | 15,000 | 1,948.05 | ||
| 3 loads "Laboule" sand | 3,000 | 389.61 | ||
| 320 bags cement | 16,000 | 2,077.92 | ||
| Rental of pouring supplies | 12,000 | 1,558.44 | ||
| Transporataion | 2,000 | 259.74 | ||
| Sub total for top slab | 9,766.23 | |||
| Total costs for basic 1st floor | 26,651.95 | |||
| Funds on hand | 20,300.00 | |||
| Shortage to complete 1st floor | -6,351.95 | |||
| Additional projects for occupancy | ||||
| Construct toilets and septic | 5,500.00 | |||
| Front of building (current floor level is 4 feet) | 4,700.00 | |||
| Grand total shortage for occupancy | -16,551.95 |